Studewood MKT Bridge Closed (Reopened Jun 2026)

Status:

Resolved
January 25, 2025

June 11, 2026

Feb 2025
Initial estimates – reopening by May 2025

April 2025
TxDOT received bridge condition assessment on 4/7/25 Structural repairs expected to begin in August Reopening expected between October and November

May 2025
Materials ordered

Sep 2025
Webber LLC (TxDOT Contractor) atively addressing review comments from Harris County Flood Control District (HCFCD). Once the updates are complete, Webber will resubmit the revised drawings through HCFCD e-permit system for review an approval with estimate resubmittal date by end of September